Railway Restored After Rockfall in Zabaykalsky Krai
Restoration of the railway line after a rockfall on the Kruchina–Novaya section of the Zabaykalskaya Railway in Zabaykalsky Krai was completed, with train traffic resumed in both directions. All delayed trains are now operating on their scheduled routes.
Consensus
- Restoration works at the Kruchina–Novaya railway section in Zabaykalsky Krai were completed.
- Train traffic resumed in both directions in normal mode.
- All delayed trains are now following their scheduled routes.
- Over 200 railway workers and specialized equipment were involved in the restoration.
- More than 140 meters of railway tracks were restored.
- No casualties were reported.
- The incident occurred on a Wednesday during the day.
- An operational headquarters was established by OAO
- RZD
Coverage (5 sources)
- Works at the site of rock collapse on the Kruchina – Novaya Zabaikalsky section in Zabaikalsky have been completed — Вести
- Movement on Trans-Siberian after rock collapse in Zabaikaly fully restored — Интерфакс
- Railway traffic on the Zabaikalsky Railway has been restored on one track — Интерфакс
- Train movement on a single track section of the Zabaykalsky railway is open — Вести
- Train movement suspended due to rock collapse on Trans-Siberian Railway in Zabaikalsky — Интерфакс