Moscow Metro Construction Hits 5-Year High
Construction work continues on the Troitskaya and Rublevskaya-Arkhangelskaya lines, as well as the Dostoevskaya station of the Circle Line.
Consensus
- Moscow's metro construction reached its maximum pace in five years in 2026.
- 14.7 kilometers of tunnels were laid in the first seven months of 2026.
- 25 stations were under construction and 10 tunnel boring machine complexes were in operation.
- The construction of the Arbatsko-Pokrovskaya Line extension to Golyanovo was completed.
- The line will be extended beyond the MKAD into the Eastern district.
- Work continues on the Troitskaya and Rublevsko-Arhangelskaya lines, as well as the Dostoyevskaya station on the Circle Line.
- Tunneling is underway for the Biryulevskaya Line.
- By 2030, 69.1 kilometers of new lines, 29 stations, and three new depots are planned.
- Since 2011, the Moscow Metro network has nearly doubled in size.
- Over 270 kilometers of lines have been laid, 127 stations built or reconstructed, and 14 depots (including MCK) constructed.
- The station 'Yuzhny Port' on the Lyublinskaya-Dmitrovskaya Line will be opened by 2030.
Points of divergence
- Construction of the 'Lipetskaya' and 'Lebedyanskaya' stations on the Biryulevskaya Line has begun. — ntv
- Construction of the 'Lipovaya Roshcha' station on the Rublevsko-Arhangelskaya Line is 50% complete, with earthworks and retaining structures finished and monolithic structures currently being installed. — m24
- The first section of the Biryulevskaya Line ('ZIL — Kuryanovo') is planned for completion in 2028, and the second section ('Kuryanovo — Biryulevo') in 2029. — ntv
- The 'Yuzhny Port' station will be designed in an industrial architectural style. — vm
Coverage (3 sources)
- Sobyanin: Metro construction reached maximum pace in five years — Вечерняя Москва
- Sobyanin called the pace of metro construction in the capital maximum for five years — НТВ Москва
- Sobyanin: metro construction reached maximum pace in five years — Москва 24