Irkut Plant to Deliver 8 MS-21s to Aeroflot in 2027
The production of the second batch of medium-range MS-21 aircraft for Aeroflot will begin with 14 units in 2029, said Andrey Soynov, general director of the Yakovlev branch of PJSC (part of the state corporation Rostec), to the press.
Consensus
- Irkutsk Aviation Plant (a branch of PAO 'Yakovlev', part of United Aircraft Corporation under Rostec) will deliver 8 MS-21 aircraft to Aeroflot in 2027.
- A second contract with Aeroflot for 90 MS-21 aircraft was signed, with deliveries scheduled from 2029 to 2023.
- The first delivery of the second batch will be 14 aircraft in 2029, followed by 18 in 2030, 24 in 2031, and 34 in 2032.
- The plant's production capacity is fully loaded until 2032.
- The MS-21 is a domestic medium-haul passenger aircraft designed to replace Tu-154 and Tu-204 fleets.
- The plant is producing components for the shortened version of the MS-21 and plans its first flight in August 2028.
- The plant plans to hire 500 new employees by the end of Q1 2027, with 170 already hired.
- The plant intends to expand production capacity through investment in machinery and equipment between 2027 and 2029.
- The plant is currently not planning to increase annual production beyond 36 aircraft.
Points of divergence
- The first MS-21s will be deployed on routes from Moscow to St. Petersburg, Kazan, Samara, and Nizhny Novgorod, with expansion to the Urals, Siberia, and southern regions. — vedomosti
- The MS-21 must complete all certification procedures by mid-2027. — kommersant
- The plant is considering future exports to 'friendly' countries after 2032. — interfax
- The plant is developing a new aircraft with a capacity exceeding 211 passengers. — interfax
- The plant will begin independently performing paint work on serial MS-21 aircraft starting in 2027. — vesti
- The first flight of the shortened MS-21 version is scheduled for August 2028. — rimao
Coverage (7 sources)
- Irkutsk Aircraft Plant will deliver eight MS-21s to Aeroflot in 2027 — Ведомости
- Irkutsk Aircraft Plant Revealed Delivery Schedule for MS-21 to Aeroflot — Коммерсантъ
- First flight of shortened version of MS-21 planned for August 2028 — Вести
- First flight of shortened MS-21 version scheduled for 2028 — РИАМО
- Contracts with "Aeroflot" for 108 MS-21 ensured full loading of IAZ until 2032 — Интерфакс
- Aeroflot will receive eight MS-21 aircraft in 2027 — Москва 24
- First flight of 'shortened' MS-21 scheduled for August 2028 — Интерфакс